December 2006 | The University Council decides on the construction of a new university building on the site of the former Hagen Castle. |
---|---|
July 2008 | Invitation to tender for the EU-wide, single-stage architectural competition |
December 2008 | The design of the architectural team Matthias Seyfert, Dietmar Moser and Susanne Seyfert from Linz (Architekturbuero 1 ZT GmbH) emerges as the winner of the tender |
April 2010 | The Upper Austrian federal government and the Upper Austrian federal parliament decide on the construction and financing of the new building |
February 2011 | The building permit is granted |
May 2011 | Groundbreaking ceremony |
June 2011 | Start of excavation |
November 2012 | Leveling ceremony |
End of 2012 | Completion of shell |
June 2014 | Start of lamella installation |
December 2014 | Completion of floor laying and painting work as well as interior finishing of the concert halls |
May 2014 | Completion of the exterior design |
Summer 2015 | Overall completion, gradual occupation and trial operation |
Autumn 2015 | Full commissioning |
November 2015 | Official opening |
February 2016 | Installation of the organ |